Commercial project
North Lakes Retirement Resort
A two-year-old resort that was never air conditioned during construction, which made the installation a far more technical job.
The job sheet.
- 01Stage 1: community hall cooled by 4x 10kW Daikin VRV ducted systems on a 40kW outdoor unit
- 02Outdoor unit positioned 50 metres from the first fan coil
- 03Indoor fan coils installed in an airtight bulkhead
- 04Stage 2: bar, cafe and dining areas on 4x Daikin VRV cassettes (7kW to 12.5kW) with a second 40kW outdoor unit 60 metres out
- 05Completed over 4 days, on time frame